All twelve property owners awarded funds have executed agreements which expire September 30, 2016. The property owners and their respective grant amounts are:
1) Winningham & Fradley 111 NE 44th St Grant $12,764
2) 91 Investment Corp 91 NE 44th St Grant $11,794
3) Hinton, Robert 75 & 87 NE 44th St Grant $19,388
4) Serabian, Charles 51 NE 44th St Grant $8,079
5) Prospect Retail, LLC 31, 41,61 NE 44th St Grant $22,620
6) Mann, Arnold/Phyllis 4400 N Andrews Ave Grant $17,611
7) Lardin, Wendy 4401 N Andrews Ave/61 NW 44th St Grant $31,991
8 )KDX Realty, LLC 121 NW 44th St Grant $8,079
9) Buttimer, Edda 141 NW 44th St Grant $8,079
10) Aiesi, Charles 181 NW 44th St Grant $8,079
11) EMB 221, LLC 222 NW 45th St Grant $8,079
12)KMR Limited, Inc 235-251 NW 44th St Grant $20,358
Although most of the property owners have started their improvements but a majority will not be complete by September 30, 2016.
Section 6 of the agreement states:
SECTION 6. EFFECTIVE DATE, TERM, COMMENCEMENT AND COMPLETION DATES
6.1 The “Effective Date” of this Agreement shall be the date of execution by the last of the parties.
6.2 The Term of this Agreement shall commence with the Effective Date and end when the parking lot construction is completed, estimated to be September 2016.
When presented to the CRA Board on February 18, 2015, the memo stated:
Project Completion
Staff recommends that property owners be given until the completion of the parking lot, currently estimated to be September 2016, to complete the façade improvements. In the event the parking lot construction interferes with the façade work, the property owners may seek additional time from the City with the understanding that the time is of the essence for the Façade Grant to be completed.
The completion of the façade upgrades and improvements are key to providing a beautiful end product at this pivotal intersection within the City and CRA.